Friday, 3 January 2025

Different Line Item Status Codes in Acknowledgment (ACK) Segment

The ACK segment in an X12 855 Purchase Order Acknowledgment is used to indicate the status of specific line items in the purchase order. 

It communicates whether the supplier accepts, rejects, or modifies the requested items in the original purchase order (850).


Structure of the ACK Segment

  • Purpose: Provides acknowledgment status codes, quantities, and other relevant details for a line item.
  • Position: The ACK segment is typically found within the detail loop in the 855 transaction.

ACK Segment Example

ACK*IA*100*EA***068*20231231~

Explanation:

  1. ACK01 (Element 668) - Line Item Status Code
    Indicates the status of the line item.
  2. ACK02 (Element 380) - Quantity
    The quantity acknowledged by the supplier.
  3. ACK03 (Element 355) - Unit of Measurement
    Unit of measurement for the quantity (e.g., EA = Each, CA = Case).
  4. ACK04 to ACK05 (Optional) - Price or Date References
    Provides additional data, such as unit price or expected shipping/delivery date.
  5. ACK06 (Element 374) - Reference Number Qualifier
    Qualifier indicating what type of reference is provided.
  6. ACK07 (Element 373) - Date
    Date relevant to the acknowledgment (e.g., delivery date).

ACK01 (Line Item Status Code) Values

Below are the most common ACK01 codes and their meanings:

Code

Description

IA

Item Accepted

IB

Item Backordered

IC

Item Accepted - Changes Made

ID

Item Deleted

IE

Item Accepted - Price Changed

IF

Item Accepted - Quantity Changed

IH

Item on Hold

IP

Item Accepted - Pending

IR

Item Rejected

IS

Item Accepted - Substitution Made

IQ

Item Accepted - Quantity and Price Changed


Key Notes

  1. Multiplicity: Each ACK segment corresponds to a single line item in the purchase order.
  2. Usage: The buyer uses the ACK segment data to understand the supplier's response to the order, such as:
    • Whether the requested items are fully available.
    • Changes to price, quantity, or delivery dates.
    • Items that are backordered, substituted, or rejected.
  3. Flexibility: Additional fields in the ACK segment can specify dates, reasons for changes, or other context.

 